“New Clinker Line Production Plant” with 1500(1900) TPD Capacity
ELAZIG CEMENT / TURKEY
We completed turnkey clinker production line with capacity 1500 (1900) TPD in Elazig/Turkey
The contract date of this Turnkey Project was January 2003. The contract value is EUR 20,000,000.-The foundation has been laid on March 2003. The dismantling of the second hand equipment; kiln line, vertical raw mill, grate cooler, pulverized coal silo and dosage system , has been accomplished in a short period of time in 3 months.
During the dismantling period, the other services were in process at the same time;
- The design and drawings of the project
- Modernization of the second hand equipment
- The procurements of the new equipments
The project started in March 2003, and the commissioning date of the rotary kiln was in March 31st, 2004. All of the turnkey services mentioned in our scope of services mentioned above are provided in 13 months. Since April 9, 2004 now the new clinker production line is in process.
DEG provided the latest version of SIEMENS Cemat based PCS 7 (version 6) in the new production line. The existing raw material supply system, the coal grinding system and the feeder units is controlled by this automation system.

|